Fwd: Lab update from 12 November

 

Hello everyone,

Apologies for missing the update yesterday. The 1SS move work is
continuing today. Rick, Larry, and Brian are continuing to work long
shifts in the lab and we're very close to having all the hardware
complete with some software services already online. The aim is to
start bringing some Jenkins systems online today, such as autopkgtest.
To be clear, we will not have everything online by the end of the day,
but tomorrow's update will include a list of what services we already
have operational and what we anticipate to be running shortly.

---------- Forwarded message ----------
From: Larry Works <larry.works@xxxxxxxxxxxxx>
Date: 13 November 2013 14:22
Subject: Lab update from 12 November
To: Evan Dandrea <evan.dandrea@xxxxxxxxxxxxx>


Greetings,

We have hardware up on the network. And, even better, it is reachable
via the VPN. We do still have a minor network issue getting the HP
managed switches tied into the rest of the Cisco network but I imagine
we'  get that resolved this morning.

 - We have 100% of the racks KVM cabled
 - We have 80% of the racks network cabled, the remaining 20% I held off
on until we get the HP to Cisco piece straight.
 - We have 60% of the hardware in the racks connected to power
 - We have to KVM switches tiered so all systems should be accessible
from a single URL


What we are going to do today:

 - Complete patching in network to the remaining 20% of systems
 - Complete connecting the remaining 40% of systems to power
 - Start bringing systems up

~w