A concrete example better than a long and difficult explanation :-)
We have the following product A composed of the product B and product B is composed from product C. So the below BOM:
A
-----B
-----------C
If the price of B is modified, then the price of A can be also modified.
But if i modify the price of C, only B is modified and not A.
This is a very important blocking issue, since in most of the real prod environment, we've of course more than 2 level of boms (in some customer installation, up to 100 levels !).
So any modification at the bottom should have a consequence on all the bom structure until the top, else OpenERP cannot be used for production.
** Affects: openobject-addons
Importance: Undecided
Status: Confirmed
** Tags: maintenance
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/702288
Title:
Cost price calculation limited to 2 levels in product bom
Status in OpenObject Addons Modules:
Confirmed
Bug description:
A concrete example better than a long and difficult explanation :-)
We have the following product A composed of the product B and product B is composed from product C. So the below BOM:
A
-----B
-----------C
If the price of B is modified, then the price of A can be also modified.
But if i modify the price of C, only B is modified and not A.
This is a very important blocking issue, since in most of the real prod environment, we've of course more than 2 level of boms (in some customer installation, up to 100 levels !).
So any modification at the bottom should have a consequence on all the bom structure until the top, else OpenERP cannot be used for production.
Follow ups
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: conexus.at, 2011-07-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Steffi Frank (Bremskerl, DE), 2011-04-02
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Ferdinand @ Camptocamp, 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Stephane Wirtel (OpenERP), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Jan Verlaan (Veritos), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Marco Dieckhoff, 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Jan Verlaan (Veritos), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Steffi Frank (Bremskerl, DE), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Fabien (Open ERP), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Steffi Frank (Bremskerl, DE), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Mark van Deursen (Neobis), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Olivier Dony (OpenERP), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Fabien (Open ERP), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Mark van Deursen (Neobis), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Fabien (Open ERP), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Jan Verlaan (Veritos), 2011-04-01
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Jan Verlaan (Veritos), 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Antony Lesuisse, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: TeMPO, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Michael Schwessinger, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Ferdinand @ Camptocamp, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: conexus.at, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Marco Dieckhoff, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Rudy, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Ferdinand @ Camptocamp, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Steffi Frank (Bremskerl, DE), 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Antony Lesuisse, 2011-03-31
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Ferdinand @ Camptocamp, 2011-01-14
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: rudy, 2011-01-14
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Steffi Frank, 2011-01-14
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: TeMPO, 2011-01-14
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: filsys, 2011-01-14
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Joël Grand-Guillaume, 2011-01-14
-
[Bug 702288] Re: Cost price calculation limited to 2 levels in product bom
From: Anup (OpenERP), 2011-01-13
-
[Bug 702288] [NEW] Cost price calculation limited to 2 levels in product bom
From: Bertrand Hanot, 2011-01-13
References