Have you used BOM Type "Sets / Phantom" for the product's BOM configuration?
Because when you will use BOM Type "Normal BoM" then it will not consider it's children 's cost, and when you will use BOM Type "Sets / Phantom" then it will be consider the children 's cost.

Thanks.

** Changed in: openobject-addons
       Status: New => Incomplete

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/705869

Title:
  Work cost of subassembly is not calc to Finish good cost

Status in OpenERP Modules (addons):
  Incomplete

Bug description:
  Steps: Sales -> Products -> Products (serach for product) and right on
  Reoprt block "Product Cost Structure".

  Error: When printing Product cost structure for a finished good that
  has subassembly in bill of material, the work cost of the subassembly
  is not calculated into the cost of finnished good.

  What should happen: The work cost of all subassemblies should be
  calculated with subassembly material cost up to finished good.

  Test made on my local computer

  OPenERP Version 6.0.0-rc2 loaded from OpenERP homepage on 4.1.2011 to
  my computer