Hello,
Have you used BOM Type "Sets / Phantom" for the product's BOM configuration?
Because when you will use BOM Type "Normal BoM" then it will not consider it's children 's cost, and when you will use BOM Type "Sets / Phantom" then it will be consider the children 's cost.
Thanks.
** Changed in: openobject-addons
Status: New => Incomplete
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/705869
Title:
Work cost of subassembly is not calc to Finish good cost
Status in OpenERP Modules (addons):
Incomplete
Bug description:
Steps: Sales -> Products -> Products (serach for product) and right on
Reoprt block "Product Cost Structure".
Error: When printing Product cost structure for a finished good that
has subassembly in bill of material, the work cost of the subassembly
is not calculated into the cost of finnished good.
What should happen: The work cost of all subassemblies should be
calculated with subassembly material cost up to finished good.
Test made on my local computer
OPenERP Version 6.0.0-rc2 loaded from OpenERP homepage on 4.1.2011 to
my computer