[Bug 705869] [NEW] Work cost of subassembly is not calc to Finish good cost

 

Public bug reported:

Steps: Sales -> Products -> Products (serach for product) and right on
Reoprt block "Product Cost Structure".

Error: When printing Product cost structure for a finished good that has
subassembly in bill of material, the work cost of the subassembly is not
calculated into the cost of finnished good.

What should happen: The work cost of all subassemblies should be
calculated with subassembly material cost up to finished good.

Test made on my local computer

OPenERP Version 6.0.0-rc2 loaded from OpenERP homepage on 4.1.2011 to my
computer

** Affects: openobject-addons
     Importance: Undecided
         Status: New

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/705869

Title:
  Work cost of subassembly is not calc to Finish good cost

Status in OpenERP Modules (addons):
  New

Bug description:
  Steps: Sales -> Products -> Products (serach for product) and right on
  Reoprt block "Product Cost Structure".

  Error: When printing Product cost structure for a finished good that
  has subassembly in bill of material, the work cost of the subassembly
  is not calculated into the cost of finnished good.

  What should happen: The work cost of all subassemblies should be
  calculated with subassembly material cost up to finished good.

  Test made on my local computer

  OPenERP Version 6.0.0-rc2 loaded from OpenERP homepage on 4.1.2011 to