[Bug 720427] Re: [6.0] crm - task - sum planned hours is missing

 

** Changed in: openobject-addons
   Importance: Undecided => Wishlist

** Changed in: openobject-addons
       Status: New => Confirmed

** Changed in: openobject-addons
     Assignee: (unassigned) => OpenERP R&D Addons Team 1 (openerp-dev-addons1)

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/720427

Title:
  [6.0] crm - task - sum planned hours is missing

Status in OpenERP Modules (addons):
  Confirmed

Bug description:
  to reproduce
  open Task from projects
  the list  shows
  * planned + remaining hours
  the sum shows
  * spent + remaining hours
  IMHO planned/spent/remaining should be listed in detail + in sums 
  same arguemntis valid for the project main page

  * planned + spent hours are displayed - missing remaining (which
  obviously is easy to calculate)