c2c-oerpscenario team mailing list archive
-
c2c-oerpscenario team
-
Mailing list archive
-
Message #22671
[Bug 768889] Re: [project]After Task scheduling, task's time not modified, and no dependencies
Hello TekseArpi,
I agree with you that Task Does not Come up with Time After
Scheduling, I request you to Open New Bug for the Timing Issues as It is
Independent issue than dependencies problem we fixed up here.
Thank You for Your Kind Support.
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/768889
Title:
[project]After Task scheduling, task's time not modified, and no
dependencies
Status in OpenERP Modules (addons):
Fix Committed
Bug description:
System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with project and Long term
planning installed.
I made a new project with 40 hr/week Working time.
I made 3 tasks: Task1, Task2 and Task3. The task's sequence number is in 11, 12, 13 respectively. I set up only the Planned hours to 10 hr.
Clicking on Compute Task Scheduling the task's date changes, accordingly, but the start and stop time is 00:00 at each task.
Each task's start date is the project's start date. Task2 start daet should be = project start date + 10hrs (Task1's planned hour).
I mean there is no dependencies, however I set up the task's sequence according to the documentation.
Then I configured Task1 as Parent task for Task2, and Task2 as Parent task for Task3, but nothing changed.
I have no dependence at all.
References