[Bug 768889] [NEW] [6.0.2][project]After Task scheduling, task's time not modified, and no dependencies

 

Public bug reported:

System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with project and Long term
planning installed.

I made a new project with 40 hr/week Working time. 
I made 3 tasks: Task1, Task2 and Task3. The task's sequence number is in 11, 12, 13 respectively.  I set up only the Planned hours to 10 hr.
Clicking on Compute Task Scheduling the task's date changes, accordingly, but the start and stop time is 00:00 at each task.

Each task's start date is the project's start date. Task2 start daet should be = project start date + 10hrs (Task1's planned hour). 
I mean there is no dependencies, however I set up the task's sequence according to the documentation. 

Then I configured Task1 as Parent task for Task2, and Task2 as Parent task for Task3, but nothing changed. 
I have no dependence at all.

** Affects: openobject-addons
     Importance: Undecided
         Status: New

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/768889

Title:
  [6.0.2][project]After Task scheduling, task's time not modified, and
  no dependencies

Status in OpenERP Modules (addons):
  New

Bug description:
  System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with project and Long term
  planning installed.

  I made a new project with 40 hr/week Working time. 
  I made 3 tasks: Task1, Task2 and Task3. The task's sequence number is in 11, 12, 13 respectively.  I set up only the Planned hours to 10 hr.
  Clicking on Compute Task Scheduling the task's date changes, accordingly, but the start and stop time is 00:00 at each task.

  Each task's start date is the project's start date. Task2 start daet should be = project start date + 10hrs (Task1's planned hour). 
  I mean there is no dependencies, however I set up the task's sequence according to the documentation. 

  Then I configured Task1 as Parent task for Task2, and Task2 as Parent task for Task3, but nothing changed. 
  I have no dependence at all.