[Bug 772654] Re: [6.0.2]Gantt view incorrect displays task end date

 

Hello,

I think in your scenario are missing 3 things, or I wasn't clear enough, sorry.
1. you didn't set up a working time,
2. Task1 is not parent (Delegations) of Task2
3. You didn't clicked Compute Task Scheduling.

Attached 3 picture.  
In 1st, and 2nd, please notice the Start and End date of the Tasks.
In 3rd you can see that Task2 is not respecting his end date.

Thanks, 
Arpi

** Attachment added: "772654 _1.png"
   https://bugs.launchpad.net/openobject-client-web/+bug/772654/+attachment/2095408/+files/772654%20_1.png

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/772654

Title:
  [6.0.2]Gantt view incorrect displays task end date

Status in OpenERP Web Client:
  Confirmed

Bug description:
  System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with Project and Long term
  planning installed.

  I made a new project with 45 hr/week Working time (9hr/day with 1 hour lunch time), starting at 25 April, 2011.
  I made 2 tasks: Task1 (planned hour: 9 hr), Task2 (36 hr). Task2's parent is Task1.

  Task Scheduler now computes OK
  (https://bugs.launchpad.net/bugs/768889,
  https://bugs.launchpad.net/bugs/771161) the Task's Starting and Ending
  date and time, and in Form view everything is OK.

  But If I switch to the Gantt view the Task2's  end date is not displayed correct. 
  Task2 starts correct at 26/04/2011 08:00 and should end 29/04/2011 18:00. But it ends 27/04/2011 20:00.

  The problem is, that Task2's end date = start date+36hour, but the
  working time is not taked in consideration.

  Thank you.
  Arpi