[Bug 772654] [NEW] [6.0.2]Gantt view incorrect displays task end date

 

Public bug reported:

System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with Project and Long term
planning installed.

I made a new project with 45 hr/week Working time (9hr/day with 1 hour lunch time), starting at 25 April, 2011.
I made 2 tasks: Task1 (planned hour: 9 hr), Task2 (36 hr). Task2's parent is Task1.

Task Scheduler now computes OK  (https://bugs.launchpad.net/bugs/768889,
https://bugs.launchpad.net/bugs/771161) the Task's Starting and Ending
date and time, and in Form view everything is OK.

But If I switch to the Gantt view the Task2's  end date is not displayed correct. 
Task2 starts correct at 26/04/2011 08:00 and should end 29/04/2011 18:00. But it ends 27/04/2011 20:00.

The problem is, that Task2's end date = start date+36hour, but the
working time is not taked in consideration.

Thank you.
Arpi

** Affects: openobject-client-web
     Importance: Undecided
         Status: New

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/772654

Title:
  [6.0.2]Gantt view incorrect displays task end date

Status in OpenERP Web Client:
  New

Bug description:
  System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with Project and Long term
  planning installed.

  I made a new project with 45 hr/week Working time (9hr/day with 1 hour lunch time), starting at 25 April, 2011.
  I made 2 tasks: Task1 (planned hour: 9 hr), Task2 (36 hr). Task2's parent is Task1.

  Task Scheduler now computes OK
  (https://bugs.launchpad.net/bugs/768889,
  https://bugs.launchpad.net/bugs/771161) the Task's Starting and Ending
  date and time, and in Form view everything is OK.

  But If I switch to the Gantt view the Task2's  end date is not displayed correct. 
  Task2 starts correct at 26/04/2011 08:00 and should end 29/04/2011 18:00. But it ends 27/04/2011 20:00.

  The problem is, that Task2's end date = start date+36hour, but the
  working time is not taked in consideration.

  Thank you.
  Arpi