c2c-oerpscenario team mailing list archive
-
c2c-oerpscenario team
-
Mailing list archive
-
Message #24084
[Bug 751401] Re: [PS] Problem with progression bar while encoding work done
** Changed in: openobject-addons
Status: Triaged => Confirmed
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/751401
Title:
[PS] Problem with progression bar while encoding work done
Status in OpenERP Modules (addons):
Confirmed
Bug description:
trunk, revno 3377
* Project/Project/Task, encode a new task with planned amount 8 hours
* Start the task and indicate you work on it for 8 hours
Obtained result : The progression bar is now at 99.9%
Expected result : the progression bar indicates 100%
reported by dha, OpenERP Prof. Services
References