A task is at 100% only when it's done,
The 99,99% is there to remind you either to set the task to done
either to reevaluate the time needed for this task.

The problem is there is no automatic way to set the progress of a task, so it's evaluate by the time spend/ time planned
that is not entirely true.  

the 99.99% is confusing but we do not have a better idea right now.

What I propose is to add in the help text of progress : "if the task has
a progress of 99.99% you should close the task if it's finished or
reevaluate the time"

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/751401

Title:
  [PS] Problem with progression bar while encoding work done

Status in OpenERP Modules (addons):
  Confirmed

Bug description:
  trunk, revno 3377

  * Project/Project/Task, encode a new task with planned amount 8 hours
  * Start the task and indicate you work on it for 8 hours

  Obtained result : The progression bar is now at 99.9%

  Expected result : the progression bar indicates 100%

  reported by dha, OpenERP Prof. Services