[Bug 873212] Re: Compute phase scheduling doesn`t compute correctly

 

Hello John,

I have checked your bug report but you didn't specified about your
phase's  sequence.

If one project phase have more then one parent phases then it will be commuted based on according to parent phases 's sequence.
Which parent project has lower sequence it will be computed first .

So Would you please describe what's  sequence you have assign for parent
project.

Thanks and waiting for your reply!

** Changed in: openobject-addons
       Status: New => Incomplete

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to OpenERP Project Group.
https://bugs.launchpad.net/bugs/873212

Title:
  Compute phase scheduling doesn`t compute correctly

Status in OpenERP Addons (modules):
  Incomplete

Bug description:
  We are using OpenErp 6.0.3 with module long_term_planning (trunk, because the previous one doesn`t work well)
  When trying to compute phase scheduling of a Project with phases that have multiple Parents phases, it computes wrong if one of Parent phase is changed - e.g.:
  Phase C has 2 parents - Phase A (duration 5h), Phase B (duration 4h).  
  Firstly Phase C is correctly computed after Phase A. But if you change duration of Phase B on 6h, then after Compute Phase Sceduling, the Phase C is STILL after Phase A instead of Phase B.