[Bug 873212] [NEW] Compute phase scheduling doesn`t compute correctly

 

Public bug reported:

We are using OpenErp 6.0.3 with module long_term_planning (trunk, because the previous one doesn`t work well)
When trying to compute phase scheduling of a Project with phases that have multiple Parents phases, it computes wrong if one of Parent phase is changed - e.g.:
Phase C has 2 parents - Phase A (duration 5h), Phase B (duration 4h).  
Firstly Phase C is correctly computed after Phase A. But if you change duration of Phase B on 6h, then after Compute Phase Sceduling, the Phase C is STILL after Phase A instead of Phase B.

** Affects: openobject-addons
     Importance: Undecided
         Status: New

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to OpenERP Project Group.
https://bugs.launchpad.net/bugs/873212

Title:
  Compute phase scheduling doesn`t compute correctly

Status in OpenERP Addons (modules):
  New

Bug description:
  We are using OpenErp 6.0.3 with module long_term_planning (trunk, because the previous one doesn`t work well)
  When trying to compute phase scheduling of a Project with phases that have multiple Parents phases, it computes wrong if one of Parent phase is changed - e.g.:
  Phase C has 2 parents - Phase A (duration 5h), Phase B (duration 4h).  
  Firstly Phase C is correctly computed after Phase A. But if you change duration of Phase B on 6h, then after Compute Phase Sceduling, the Phase C is STILL after Phase A instead of Phase B.