[Bug 873212] Re: Compute phase scheduling doesn`t compute correctly

 

Hello Jonh,

I have read your comment, I am not agree with you this is not a bug but
it's your configuration problem.

The project phase order on four filed that is project_id, date_start,
sequence, name so we need to configure data based on this Configuration
because in project phase  _order = "project_id, date_start, sequence,
name" so the name is last priority.

So Would you please configure based on this configuration.

Hope this will help for you.
Correct me If I am wrong

Thanks.

** Changed in: openobject-addons
       Status: Incomplete => Invalid

** Converted to question:
   https://answers.launchpad.net/openobject-addons/+question/175047

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to OpenERP Project Group.
https://bugs.launchpad.net/bugs/873212

Title:
  Compute phase scheduling doesn`t compute correctly

Status in OpenERP Addons (modules):
  Invalid

Bug description:
  We are using OpenErp 6.0.3 with module long_term_planning (trunk, because the previous one doesn`t work well)
  When trying to compute phase scheduling of a Project with phases that have multiple Parents phases, it computes wrong if one of Parent phase is changed - e.g.:
  Phase C has 2 parents - Phase A (duration 5h), Phase B (duration 4h).  
  Firstly Phase C is correctly computed after Phase A. But if you change duration of Phase B on 6h, then after Compute Phase Sceduling, the Phase C is STILL after Phase A instead of Phase B.

To manage notifications about this bug go to: