[Bug 873212] Re: Compute phase scheduling doesn`t compute correctly
Hello Jonh,
I have read your comment, I am not agree with you this is not a bug but
it's your configuration problem.
The project phase order on four filed that is project_id, date_start,
sequence, name so we need to configure data based on this Configuration
because in project phase _order = "project_id, date_start, sequence,
name" so the name is last priority.
So Would you please configure based on this configuration.
Hope this will help for you.
Correct me If I am wrong
Thanks.
** Changed in: openobject-addons
Status: Incomplete => Invalid
** Converted to question:
https://answers.launchpad.net/openobject-addons/+question/175047
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to OpenERP Project Group.
https://bugs.launchpad.net/bugs/873212
Title:
Compute phase scheduling doesn`t compute correctly
Status in OpenERP Addons (modules):
Invalid
Bug description:
We are using OpenErp 6.0.3 with module long_term_planning (trunk, because the previous one doesn`t work well)
When trying to compute phase scheduling of a Project with phases that have multiple Parents phases, it computes wrong if one of Parent phase is changed - e.g.:
Phase C has 2 parents - Phase A (duration 5h), Phase B (duration 4h).
Firstly Phase C is correctly computed after Phase A. But if you change duration of Phase B on 6h, then after Compute Phase Sceduling, the Phase C is STILL after Phase A instead of Phase B.