← Back to team overview

credativ team mailing list archive

[Bug 922669] Re: [R6.1 rc1]: Project Mgt: Gantt view: always showing 100% completion on tasks

 

*** This bug is a duplicate of bug 908764 ***
    https://bugs.launchpad.net/bugs/908764

** Project changed: openobject-addons => openerp-web

** Changed in: openerp-web
     Assignee: (unassigned) => OpenERP R&D Web Team (openerp-dev-web)

** This bug has been marked a duplicate of bug 908764
   web gantt view

-- 
You received this bug notification because you are a member of OpenERP
Framework Experts, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/922669

Title:
  [R6.1 rc1]: Project Mgt: Gantt view: always showing 100% completion on
  tasks

Status in OpenERP Web:
  New

Bug description:
  Using OpenERP R6.1 rc1

  Installed scrum and longterm planning

  When I look at the gantt chart view, showing the tasks. They are all
  showing that the tasks are 100% completed, even though it is not the
  case.

  When I open the task in form view, the percentage of completion is
  calculated correctly in the progress bar

To manage notifications about this bug go to:
https://bugs.launchpad.net/openerp-web/+bug/922669/+subscriptions


References