[Bug 922669] Re: [R6.1 rc1]: Project Mgt: Gantt view: always showing 100% completion on tasks
*** This bug is a duplicate of bug 908764 ***
https://bugs.launchpad.net/bugs/908764
** Project changed: openobject-addons => openerp-web
** Changed in: openerp-web
Assignee: (unassigned) => OpenERP R&D Web Team (openerp-dev-web)
** This bug has been marked a duplicate of bug 908764
web gantt view
--
You received this bug notification because you are a member of OpenERP
Framework Experts, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/922669
Title:
[R6.1 rc1]: Project Mgt: Gantt view: always showing 100% completion on
tasks
Status in OpenERP Web:
New
Bug description:
Using OpenERP R6.1 rc1
Installed scrum and longterm planning
When I look at the gantt chart view, showing the tasks. They are all
showing that the tasks are 100% completed, even though it is not the
case.
When I open the task in form view, the percentage of completion is
calculated correctly in the progress bar