← Back to team overview

linaro-project-management team mailing list archive

Re: Allocation via a spreadsheet: simple but effective way to do resource allocations

 

On 12 May 2011, at 16:00, anmar.oueja@xxxxxxxxxx wrote:

> On 12 May 2011 09:36, Fathi Boudra <fathi.boudra@xxxxxxxxxx> wrote:
>> 
>> We need a prerequisite: an accurate list of the resources (person/team).
>> 
>> I'm trying to get the list of team member (in my case Platform) and my
>> current inputs aren't good enough:
>> - MeetTheTeam isn't up-to-date
> 
> I suggest you go after the platform team to make sure they are updated
> by next week and i will chase the landing teams to make sure that they
> are also up to date.

Please talk to Arwen about this, she is the point of contact for the
MeetTheTeam page.

> cheers,
> 
> anmar

Regards,
Jamie.
--
Linaro Release Manager    |  Platform Project Manager
Office: +44 1761 348 220  |  Mobile: +44 7962 259 437



Follow ups

References