Re: Can we implement kiko's proposed roadmap flow by the next Connect? (was Re: Updated Roadmap to BP slide deck)
On Fri, Aug 12, 2011 at 10:57:31AM +0200, Alexander Sack wrote:
> When discussing the monthly model, I got feedback from techleads and
> PMs that they would like to keep a single page that tracks all the
> blueprints and work items for the upcoming milestones of all
> components the team participates in.
For /all/ upcoming milestones? Is this basically a backlog view, or a
view for what's already planned for coming months?
> Proposal for Team Page:
> * current monthly milestone team page becomes a "upcoming milestones
> for team" page
Are you referring to the page on s.l.o? I.e:
http://status.linaro.org/11.11/linaro-android.html
If so, is the main change here having it rolled up into milestones?
> * work item burn down gets killed because there might be conflicting
> dates - also I believe a burn down for just a month is often not that
> meaningful.
Does any burn down chart at all make sense? On the lane level only
perhaps?
> * status by blueprint becomes "upcoming deliverables"; grows columns:
> component name + milestone + days left till delivery
And work items?
I keep on wondering if we're not better off doing this in Launchpad. It
sounds like what we want is closer to LP than s.l.o.
--
Christian Robottom Reis, Engineering VP