Re: FOR YOUR ATTENTION: Virtual Connect - closing out cards

 

On 17 July 2012 08:30, Ilias Biris <ilias.biris@xxxxxxxxxx> wrote:
> Hmm
>
> I guess that the attached thread is somehow forgotten by some?
>
> In my understanding the current cycle ends on the 10th of August. The
> next cycle goes from 20 August to the next face to face Connect. The
> period between 10 and 20 August is when we would do a "virtual connect"
> - ie discuss over the items to complete during the period up to the next
> face to face Connect.

Can we end the quarter on the same date we end the next monthly cycle,
on August 30th? If we end it on the 10th then we'll only be able to
deliver things that we've been working on in 12.07.

> What this means in terms of the roadmap is we should have the Q2 cards
> completing within the period till 10 August.
>
> Are there any of these cards which are at risk of not being ready by
> then? Which ones?

Both of mine are at risk, if we close out on this date.

>
> Thanks,
>
> Ilias
>
>
>> On Tue, Jul 17, 2012 at 2:26 AM, Ilias Biris <ilias.biris@xxxxxxxxxx> wrote:
>>> Hello Tech Leads
>>>
>>> As the virtual connect target week is approaching I would like to
>>> finalise any arrangements for the closing out of cards.
>>>
>>> As a reminder the target (as I know of it) week is the week ending 17
>>> August. This means the work behind the roadmap cards should be
>>> completed, and the card closeout sections in place by Fri 10 August.
>>>
>>> Whilst the VC is being setup, I would like to have separate sessions
>>> during that period with each one of you, in order to go through the
>>> cards closeouts and make the final recommendations to the OPSCOM/TSC.
>>> The point is to have 1 meeting rather than a series of emails.
>>>
>>> My aim is to have those meetings on the period 15 August - 22 August, as
>>> I will be offline before the 15th. Is that acceptable?
>>>
>>> The means will be google hangouts. I hope that works too.
>>>
>>> If you have any concerns with these suggestions please shout out. I will
>>> be sending invitations through google calendar over the next 2-3 days.
>>> Please note I will be on vac starting 18 Jul (tomorrow), but will
>>> allocate some evening time until the end of this week to send out all
>>> invitations.
>>>
>>> BR,
>>>
>>> --
>>> Ilias Biris ilias.biris@xxxxxxxxxx
>>> Project Manager, Linaro
>>> M: +358504839608, IRC: ibiris Skype: ilias_biris
>>> Linaro.org│ Open source software for ARM SoCs
>>>
>
>
> --
> Ilias Biris ilias.biris@xxxxxxxxxx
> Project Manager, Linaro
> M: +358504839608, IRC: ibiris Skype: ilias_biris
> Linaro.org│ Open source software for ARM SoCs
>
>



-- 
Zach Pfeffer
Android Platform Team Lead, Linaro Platform Teams
Linaro.org | Open source software for ARM SoCs
Follow Linaro: http://www.facebook.com/pages/Linaro
http://twitter.com/#!/linaroorg - http://www.linaro.org/linaro-blog


References