← Back to team overview

openerp-india team mailing list archive

[Bug 922669] [NEW] [R6.1 rc1]: Project Mgt: Gantt view: always showing 100% completion on tasks

 

Public bug reported:

Using OpenERP R6.1 rc1

Installed scrum and longterm planning

When I look at the gantt chart view, showing the tasks. They are all
showing that the tasks are 100% completed, even though it is not the
case.

When I open the task in form view, the percentage of completion is
calculated correctly in the progress bar

** Affects: openobject-addons
     Importance: Undecided
         Status: New


** Tags: r6.1 rc1

-- 
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/922669

Title:
  [R6.1 rc1]: Project Mgt: Gantt view: always showing 100% completion on
  tasks

Status in OpenERP Addons (modules):
  New

Bug description:
  Using OpenERP R6.1 rc1

  Installed scrum and longterm planning

  When I look at the gantt chart view, showing the tasks. They are all
  showing that the tasks are 100% completed, even though it is not the
  case.

  When I open the task in form view, the percentage of completion is
  calculated correctly in the progress bar

To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/922669/+subscriptions