Hello Charton,
As per the bug lp:959219 , project_long_term plan to remove from trunk.
So It's not more further enhance.
Moreover, you talk about change functionality of project management.
That's why I am set this Issue as Won't Fix.
Thanks!
** Changed in: openobject-addons
Status: New => Won't Fix
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1061205
Title:
Problems on Project Management openerp 6.1
Status in OpenERP Addons (modules):
Won't Fix
Bug description:
Hi everyone.
I try to manage projects on openerp 6.1, lots of problems:
* tasks & phases dates are not escalating automatically : when you
change a parent task, children start & end dates should be updated.
* resources allocation has been removed!!!!
I'm looking to the code to implement, suggestions are welcomed
To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/1061205/+subscriptions