Re: [Bug 1061205] Re: Problems on Project Management openerp 6.1

 

Le 05/10/2012 08:26, Amit Bhavsar (Open ERP) a écrit :
> Hello Charton,
>
> As per the bug lp:959219 ,  project_long_term plan to remove from trunk.
> So It's not more further enhance.
>
> Moreover, you talk about change functionality of project management.
> That's why I am set this Issue as Won't Fix.
>
>
> Thanks!
>
> ** Changed in: openobject-addons
>         Status: New => Won't Fix
>
Hi & thanks for your answer.

Where can I put suggestions of developpement ?

I'm going to code tasks escalating & tasks's resources allocations, lots 
of openerp users a looking forward to it, so i'd like to share it.

If you can give me a summary of the way I must reference it on lp so 
everyone can follow & comment & even help or request, i'll appreciate 
(lake of time to consult all readmes...)

Thanks a lot.

Jeremie.

-- 
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1061205

Title:
  Problems on Project Management openerp 6.1

Status in OpenERP Addons (modules):
  Won't Fix

Bug description:
  Hi everyone.

  I try to manage projects on openerp 6.1, lots of problems:

  * tasks & phases dates are not escalating automatically : when you
  change a parent task, children start & end dates should be updated.

  * resources allocation has been removed!!!!

  I'm looking to the code to implement, suggestions are welcomed