[Bug 764281] [NEW] MRP: Setting one work order to "In progress" sets all work orders to "In Progress"
Public bug reported:
Steps to reproduce:
1) Create a manufacturing order (MO) for a product using a bill of materials and a routing with several steps. Confirm the MO.
2) Open up the MO in form view and click on the "Work Orders" tab.
3) Click on the first work order "start icon" to put it into the "In Progress" state
Observed result:
All work orders are put into the "In Progress" state, not just the one selected
Expected result:
Only the work order selected should be set to the "In Progress" state
Platform:
OpenERP V6.02, Server 3401, Client 1835, Add-ons 4526
** Affects: openobject-addons
Importance: Undecided
Status: New
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/764281
Title:
MRP: Setting one work order to "In progress" sets all work orders to
"In Progress"
Status in OpenERP Modules (addons):
New
Bug description:
Steps to reproduce:
1) Create a manufacturing order (MO) for a product using a bill of materials and a routing with several steps. Confirm the MO.
2) Open up the MO in form view and click on the "Work Orders" tab.
3) Click on the first work order "start icon" to put it into the "In Progress" state
Observed result:
All work orders are put into the "In Progress" state, not just the one selected
Expected result:
Only the work order selected should be set to the "In Progress" state
Platform:
OpenERP V6.02, Server 3401, Client 1835, Add-ons 4526
Follow ups