[Bug 772654] Re: [6.0.2]Gantt view incorrect displays task end date
Hello,
As I can see on your 2nd video:
1. Task dependence (delegations) not working however (as I saw ) you set up the parent task. This was fixed in in rev. 4649 (https://bugs.launchpad.net/bugs/768889).
Your Task2 starts in 04/25/2011 but it should start only in 04/26/2011 (2nd video, 0:31) after Task1 is finished, because Task1 is parent for Task2.
2. Task1 on Gantt ends in 04/26/2011 01:00 o'clock, (2nd video, 0:38) but it should end next day at 11:00 o'clock according to the working time. Day 04/25 works 8 hr, from 10-19, and 04/26 works 1 hr, from 10-11.
This is the bug I'm talking about.
(I modified manually my code according this bug:
https://bugs.launchpad.net/openobject-addons/+bug/771161, to be able to
see in form view the Task's starting and ending hours.)
Thank you for your patience, and sorry if I'm not clear every time.
Arpi
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/772654
Title:
[6.0.2]Gantt view incorrect displays task end date
Status in OpenERP Web Client:
Confirmed
Bug description:
System: Ubuntu 10.10. OERP 6.0.2. Fresh db, with Project and Long term
planning installed.
I made a new project with 45 hr/week Working time (9hr/day with 1 hour lunch time), starting at 25 April, 2011.
I made 2 tasks: Task1 (planned hour: 9 hr), Task2 (36 hr). Task2's parent is Task1.
Task Scheduler now computes OK
(https://bugs.launchpad.net/bugs/768889,
https://bugs.launchpad.net/bugs/771161) the Task's Starting and Ending
date and time, and in Form view everything is OK.
But If I switch to the Gantt view the Task2's end date is not displayed correct.
Task2 starts correct at 26/04/2011 08:00 and should end 29/04/2011 18:00. But it ends 27/04/2011 20:00.
The problem is, that Task2's end date = start date+36hour, but the
working time is not taked in consideration.
Thank you.
Arpi