[Bug 791207] Re: [6.1 trunk]:[project] task progress wrong

 

Hello Bogdan,

I have checked your issue but I don't agree with you.

Whenever your task is done i.e after pressing "DONE" button than and
than only your progress bar is 100%, otherwise it will show 99.99%.
Because your task currently is in progress state.

I have attached a video for your reference.

So this is not a bug and I am closing this issue.

Thank you.

** Changed in: openobject-addons
       Status: New => Invalid

** Converted to question:
   https://answers.launchpad.net/openobject-addons/+question/160127

-- 
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/791207

Title:
  [6.1 trunk]:[project] task progress wrong

Status in OpenERP Modules (addons):
  Invalid

Bug description:
  hello!

  While using the module Project,
  Project > Project >Tasks
  I create a new task, with e.g. 5h estimated time.
  then I add work done 5h 

  the progress bar stops at 99.99% instead of 100%