Re: [RFC] Change to release management process
2009/10/12 Jonathan Lange <jml@xxxxxxxxxxxxx>:
> On Mon, Oct 12, 2009 at 5:15 PM, Graham Binns <graham@xxxxxxxxxxxxx> wrote:
>> 2009/10/12 Jonathan Lange <jml@xxxxxxxxxxxxx>:
>>> That's a good suggestion. It raises two questions, neither of which I
>>> know the answer to:
>>>
>>> - why would there open bugs on the milestone after we've frozen the code?
>>
>> Because there's a finite amount of time in a developer's day, and
>> sometimes we think we're able to get things finished but life gets in
>> the way.
>>
>
> I haven't been as clear as I ought. Sorry.
>
> In the plan I described, I had meant for the RM to go through the
> milestone at some time shortly after code freeze and move the bugs
> that are:
> a) on the milestone
> b) open
> c) not release critical
>
> off the milestone. I say "shortly after" to allow developers time to
> retarget the bugs themselves.
>
> My question, now that I think about it, would have been better phrased
> as "What's the point of having open, non-release-critical bugs on the
> milestone after code freeze?". I think the answer is "there is none".
What I'm suggesting is that developers will take care to remove bugs
that have missed the milestone, and the RM (or whoever else has the
authority) sets the importance to Critical if it isn't already, if
they agree that the bug should be considered release-critical.