Le 20/04/10 12:21, Olivier Dony a écrit :
I'm not sure why you actually need an additional module for this?
Until the sale.order is confirmed, the actual delivery date per line is
a moving thing, which is computed as:
s.o date + s.o.l. customer lead time + company safety lead time
I've tested today and the calculation is
Date now + s.o.l customer lead time - company safety lead time
Normaly :
Date now + s.o.l customer lead time + company safety lead time
No ?
--
Sébastien LANGE
SYLEAM Info Services
Gold Partner Open ERP
begin:vcard
fn:Sebastien LANGE
n:LANGE;Sebastien
org:SYLEAM Info Services
adr:;;27 avenue Jean Mantelet;ALENCON;;61000;FRANCE
email;internet:sebastien.lange@xxxxxxxxx
title:CEO
tel;work:+33 2 33 31 22 10
tel;fax:+33 2 33 31 22 14
note:Gold Partner Open ERP
x-mozilla-html:FALSE
url:http://www.Syleam.fr
version:2.1
end:vcard
Follow ups
References