Hello All,
I am facing a problem in subcontracting process in OpenERP 6.0.
I am configuring OpenERP for wire manufacturing industry and facing
problem in subcontracting process.
The Process:
In manufacturing of wire, components required are Conductor and Insulation Tape(s). Tape is manufactured in-house and for conductor raw material (Silver & Copper) is provided to supplier which in turns returns the finished conductor.
What I have configured:
I have created a finished product BOM i.e. for Wire with components as Conductor and Tape.
And for conductor manufacturing,
1. I have created a subcontracting supplier location which I have assigned in “Production Location” field in Conductor Manufacturing Routing.
2. Created a BOM for conductor manufacturing with components as Silver and Copper.
Whenever I creates a Manufacturing Order for finished product, a new
manufacturing order is generated for conductor manufacturing which is
fine, a delivery order (Silver and Copper delivery to subcontracting
supplier) which is again OK and an incoming shipment.
Till delivery order every thing is fine, but in incoming shipment lines
system shows raw material entries instead of conductor entry.
Please help, did I configured incorrectly or there this is a bug in
openERP.
Thanks in advance.
** Affects: openobject-addons
Importance: Undecided
Status: New
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1025140
Title:
Subcontracting Process - Incoming shipment receives raw material sent
to supplier.
Status in OpenERP Addons (modules):
New
Bug description:
Hello All,
I am facing a problem in subcontracting process in OpenERP 6.0.
I am configuring OpenERP for wire manufacturing industry and facing
problem in subcontracting process.
The Process:
In manufacturing of wire, components required are Conductor and Insulation Tape(s). Tape is manufactured in-house and for conductor raw material (Silver & Copper) is provided to supplier which in turns returns the finished conductor.
What I have configured:
I have created a finished product BOM i.e. for Wire with components as Conductor and Tape.
And for conductor manufacturing,
1. I have created a subcontracting supplier location which I have assigned in “Production Location” field in Conductor Manufacturing Routing.
2. Created a BOM for conductor manufacturing with components as Silver and Copper.
Whenever I creates a Manufacturing Order for finished product, a new
manufacturing order is generated for conductor manufacturing which is
fine, a delivery order (Silver and Copper delivery to subcontracting
supplier) which is again OK and an incoming shipment.
Till delivery order every thing is fine, but in incoming shipment
lines system shows raw material entries instead of conductor entry.
Please help, did I configured incorrectly or there this is a bug in
openERP.
Thanks in advance.
To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/1025140/+subscriptions
Follow ups
-
[Bug 1025140] Re: Subcontracting Process - Invoicing process doesn't correct
From: Naresh(OpenERP), 2012-09-26
-
[Bug 1025140] Re: Subcontracting Process - Invoicing process doesn't correct
From: Element Green, 2012-08-17
-
[Bug 1025140] Re: Subcontracting Process - Invoicing process doesn't correct
From: Rakesh, 2012-07-27
-
[Bug 1025140] Re: Subcontracting Process - Invoicing process doesn't correct
From: Steffi Frank (Bremskerl, DE), 2012-07-26
-
[Bug 1025140] Re: Subcontracting Process - Invoicing process doesn't correct
From: Steffi Frank (Bremskerl, DE), 2012-07-26
-
[Bug 1025140] Re: Subcontracting Process - Invoicing process doesn't correct
From: Amit Parik (OpenERP), 2012-07-26
-
[Bug 1025140] Re: Subcontracting Process - Raw material's Delivery order doesn't created If product 's procure method='buy' .
From: Amit Parik (OpenERP), 2012-07-26
-
[Bug 1025140] Re: Subcontracting Process - Raw material's Delivery order doesn't created If product 's procure method='buy' .
From: Mannu Sharma, 2012-07-26
-
[Bug 1025140] Re: Subcontracting Process - Raw material's Delivery order doesn't created If product 's procure method='buy' .
From: Steffi Frank (Bremskerl, DE), 2012-07-24
-
[Bug 1025140] Re: Subcontracting Process - Raw material's Delivery order doesn't created If product 's procure method='buy' .
From: Amit Parik (OpenERP), 2012-07-23
-
[Bug 1025140] Re: Subcontracting Process - Raw material's Delivery order doesn't created If product 's procure method='buy' .
From: Steffi Frank (Bremskerl, DE), 2012-07-21
-
[Bug 1025140] Re: Subcontracting Process - Raw material's Delivery order doesn't created If product 's procure method='buy' .
From: Mannu Sharma, 2012-07-21
-
[Bug 1025140] Re: Subcontracting Process - Raw material's Delivery order doesn't created If product 's procure method='buy' .
From: Amit Parik (OpenERP), 2012-07-20
-
[Bug 1025140] Re: Subcontracting Process - Raw material's Delivery order doesn't created If product 's procure method='buy' .
From: Mannu Sharma, 2012-07-20
-
[Bug 1025140] Re: Subcontracting Process - Incoming shipment receives raw material sent to supplier.
From: Amit Parik (OpenERP), 2012-07-20
-
[Bug 1025140] Re: Subcontracting Process - Incoming shipment receives raw material sent to supplier.
From: Mannu Sharma, 2012-07-20
-
[Bug 1025140] Re: Subcontracting Process - Incoming shipment receives raw material sent to supplier.
From: Amit Parik (OpenERP), 2012-07-20
-
[Bug 1025140] Re: Subcontracting Process - Incoming shipment receives raw material sent to supplier.
From: Amit Parik (OpenERP), 2012-07-20
-
[Bug 1025140] Re: Subcontracting Process - Incoming shipment receives raw material sent to supplier.
From: Mannu Sharma, 2012-07-20
-
[Bug 1025140] Re: Subcontracting Process - Incoming shipment receives raw material sent to supplier.
From: Amit Bhavsar (Open ERP), 2012-07-18
-
[Bug 1025140] Re: Subcontracting Process - Incoming shipment receives raw material sent to supplier.
From: Mannu Sharma, 2012-07-16
-
[Bug 1025140] [NEW] Subcontracting Process - Incoming shipment receives raw material sent to supplier.
From: Mannu Sharma, 2012-07-16
References