[Bug 1093403] [NEW] [7.0] Project Scheduler - No user planning and wrong dates
Public bug reported:
We are currently facing a problem with the Phases/Tasks Scheduling in version 7.0.
The scheduler doesn't seem to take into account the resources we have set, as you can see in the following lines:
- Project "RD":
Manager: User1 - Team: User1, User2 - Working Time: Tuesday (9:00-13:00 / 14:00-18:00)
- Phase "RD1":
Duration: 24 hours.
- 4 Tasks:
Duration: 6 hours
Assigned to: User2
(+ Resource "Human": User2 on Tuesday (9:00-13:00 / 14:00-18:00) but
seems it can not be use anywhere..)
1) When we run the Phase Scheduler on 24th dec, we expect a Phase from 25th December 09:00 (closest Tuesday) to the 10th January 18:00 (since we work 8 hours every tuesday, and have a 24 hours work to do, so 3 tuesdays).
The actual result is 5th December 17:00 (closest Tuesday) to the 11th January 02:00, which is 8 hours later, so it seems the problem is linked to a TimeZone setup (we are based in Shanghai, UTC +8).
=> Is it a wrong setup or a bug in the code ?
2) Then we run the Task Scheduler, and the result is empty (regardless if the Project has only Tasks or Tasks+Phases).
Here, I have no clue why nothing is created.
=> Is it a wrong setup or a bug in the code ?
** Affects: openobject-addons
Importance: Undecided
Status: New
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1093403
Title:
[7.0] Project Scheduler - No user planning and wrong dates
Status in OpenERP Addons (modules):
New
Bug description:
We are currently facing a problem with the Phases/Tasks Scheduling in version 7.0.
The scheduler doesn't seem to take into account the resources we have set, as you can see in the following lines:
- Project "RD":
Manager: User1 - Team: User1, User2 - Working Time: Tuesday (9:00-13:00 / 14:00-18:00)
- Phase "RD1":
Duration: 24 hours.
- 4 Tasks:
Duration: 6 hours
Assigned to: User2
(+ Resource "Human": User2 on Tuesday (9:00-13:00 / 14:00-18:00) but
seems it can not be use anywhere..)
1) When we run the Phase Scheduler on 24th dec, we expect a Phase from 25th December 09:00 (closest Tuesday) to the 10th January 18:00 (since we work 8 hours every tuesday, and have a 24 hours work to do, so 3 tuesdays).
The actual result is 5th December 17:00 (closest Tuesday) to the 11th January 02:00, which is 8 hours later, so it seems the problem is linked to a TimeZone setup (we are based in Shanghai, UTC +8).
=> Is it a wrong setup or a bug in the code ?
2) Then we run the Task Scheduler, and the result is empty (regardless if the Project has only Tasks or Tasks+Phases).
Here, I have no clue why nothing is created.
=> Is it a wrong setup or a bug in the code ?