← Back to team overview

openerp-india team mailing list archive

[Bug 1236782] Re: [7.0] mrp operation scheduled dates not generated

 

** Summary changed:

- mrp operation scheduled dates not generated
+ [7.0] mrp operation scheduled dates not generated

-- 
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1236782

Title:
  [7.0] mrp operation scheduled dates not generated

Status in OpenERP Addons (modules):
  New

Bug description:
  OpenERP 7.0-20131007-231023, Ubuntu 12.04 postgres 9.1

  Install fresh db with module mrp_operations.

  Create products, boms, Workcenters, routings with operations.

  If you generate MO the operations (Work Orders) doesn't contain
  Scheduled Date.

  It worked in build from openerp-7.0-20130806 but it doesn't work in
  some subsequent nightly builds.

  On the screen the black Work Orders were created using build from
  August (openerp-7.0-20130806-231058.tar.gz). The red ones are created
  using builds from late September and current

To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/1236782/+subscriptions


References