[Bug 1236782] [NEW] mrp operation scheduled dates not generated
Public bug reported:
OpenERP 7.0-20131007-231023, Ubuntu 12.04 postgres 9.1
Install fresh db with module mrp_operations.
Create products, boms, Workcenters, routings with operations.
If you generate MO the operations (Work Orders) doesn't contain
Scheduled Date.
It worked in build from openerp-7.0-20130806 but it doesn't work in some
subsequent nightly builds.
On the screen the black Work Orders were created using build from August
(openerp-7.0-20130806-231058.tar.gz). The red ones are created using
builds from late September and current
** Affects: openobject-addons
Importance: Undecided
Status: New
** Attachment added: "work_orders.png"
https://bugs.launchpad.net/bugs/1236782/+attachment/3866134/+files/work_orders.png
--
You received this bug notification because you are a member of OpenERP
Indian Team, which is subscribed to OpenERP Addons.
https://bugs.launchpad.net/bugs/1236782
Title:
mrp operation scheduled dates not generated
Status in OpenERP Addons (modules):
New
Bug description:
OpenERP 7.0-20131007-231023, Ubuntu 12.04 postgres 9.1
Install fresh db with module mrp_operations.
Create products, boms, Workcenters, routings with operations.
If you generate MO the operations (Work Orders) doesn't contain
Scheduled Date.
It worked in build from openerp-7.0-20130806 but it doesn't work in
some subsequent nightly builds.
On the screen the black Work Orders were created using build from
August (openerp-7.0-20130806-231058.tar.gz). The red ones are created
using builds from late September and current
To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/1236782/+subscriptions