Here's the latest on what is now working:

- The krillin build process is now fully enabled and builds are working.

- Smoke testing is running for both mako and krilin devices. Capacity is
limited as we have several makos that need attention from the Data Center
Engineers (who are also busy moving other kit).


And what's still offline:

- MP testing is disabled, but should be re-enabled in the next 2-3 hours.
This will initially be at very low capacity as several of the armhf
builders were lost during the move. They are being rebuilt. Phones for
testing MPs are also limited.

- The rtm-dashboard for looking at krillin smoke testing results (work in
progress).

- The proposed-migration test slaves are still having network connectivity
issues (IS has been notified).

Francis

On Tue, Dec 9, 2014 at 5:57 PM, Francis Ginther <
francis.ginther@xxxxxxxxxxxxx> wrote:

> The CI services are starting to come back online. Much is still disabled,
> but I expect to get the smoke testing enabled tonight. The krillin builds
> are also partially enabled, just need to see if the rest of the
> system-image process is properly networked. The krillin builds are
> currently a priority.
>
> The MP testing is currently still disabled while we work with IS to update
> the network and firewall connections to the build nodes. We also need to
> rebuild some of the armhf build nodes. The current ETA is to have this
> enabled tomorrow.
>
> Francis
> --
> Francis Ginther
> Canonical - Ubuntu Engineering - Continuous Integration Team
>



-- 
Francis Ginther
Canonical - Ubuntu Engineering - Continuous Integration Team