>> Thanks Blair,
>>
>> I am working on these now.  It will require more than one pass to nail all of them.
>>
>> I will let you know when the first pass is done.
> 
> 
> I am still on the first pass, with an interim progress report: fixed the initial segfault
> and committed it.
> 
> But there's still going to be a more work on pass 1 which I will do tomorrow.

That was over 10 days ago.  Sorry I've had two weekends yanked away from me.

Should very likely have some time this week.


> 
> That includes implementing paragraph 3) in the improved OpenProjectFiles() function
> comment, attached.  It will mean going through every KIWAY and testing for existence of
> aFileList[0] on disk rather than attempting to open it.  This logic was probably somewhere
> else previously.  A lot things have new homes, and some are homeless.
> 
> After that tomorrow, we can gather up things you find and call it pass 2 items.
> 
> Thanks for your help.
> 